Indian Contract Act, 1872; Specific Relief Act, 1963; Commercial Courts Act, 2015, Section 2(1)(c)(vi)

Construction Disputes Without an Arbitration Clause: Unpaid Bills, Delays, Escalation and Retention Money

Unpaid RA bills, withheld retention money, delay penalties or escalation claims with no arbitration clause? How construction suits run in Delhi NCR courts.

In short. This page is for contractors, subcontractors, developers and owners whose construction contract has no arbitration clause. Without one, a fight over unpaid bills, delay, escalation or retention money goes to a civil court. Construction contracts count as commercial disputes, so a claim of Rs 3 lakh or more lands in a Commercial Court, normally after mediation. Contested suits often run two to four years. The evidence is heavy. Before anything else, make sure there isn't an arbitration clause hiding somewhere, and get your bills, measurement records and site letters into safe hands.

सारांश (हिंदी में)यह पेज उन ठेकेदारों, सब-कॉन्ट्रैक्टरों, बिल्डरों और प्रोजेक्ट मालिकों के लिए है जिनके कॉन्ट्रैक्ट में आर्बिट्रेशन क्लॉज़ नहीं है। ऐसे में बकाया बिल, देरी, एस्केलेशन या रिटेंशन मनी का झगड़ा सीधे सिविल कोर्ट में जाता है। कंस्ट्रक्शन का मामला कमर्शियल विवाद माना जाता है, तो 3 लाख या उससे ऊपर का क्लेम हो तो पहले मीडिएशन होगा, फिर कमर्शियल कोर्ट। सामने वाला लड़े तो दो से चार साल आराम से लग जाते हैं, क्योंकि मेज़रमेंट और देरी के सबूत बहुत होते हैं। सबसे पहले पूरा कॉन्ट्रैक्ट पढ़कर पक्का कर लीजिए कि कहीं आर्बिट्रेशन क्लॉज़ छुपा तो नहीं है। फिर सारे बिल, मेज़रमेंट बुक और साइट की चिट्ठियाँ संभालकर एक जगह रख लीजिए।

Is this your situation?

  • Your RA bills come back from the client's engineer weeks late, with the measurements cut. Some don't come back at all.
  • You handed over the building in spring. The final bill is still "under scrutiny".
  • The defect liability period ended a year ago, and your retention and security deposit haven't moved.
  • The owner is docking liquidated damages for delay, when it was their revised drawings that reached site six weeks late.
  • Steel and labour rates went up while the project dragged on. Your contract says nothing clear about escalation.
  • You're the subcontractor, and the main contractor keeps telling you it'll pay when the client pays it.
  • You own the project. The contractor pulled his men off site with the work half done, and part of what he did build leaks.

Start here: is there really no arbitration clause?

Most big construction contracts do have an arbitration clause. If yours does, the dispute generally goes to arbitration rather than a civil suit, and the court work around it (petitions under Sections 9, 11 and 34 of the Arbitration and Conciliation Act, 1996) is covered on arbitrationlawyer.in. This page deals with the many contracts that don't have one. Think of work orders from private owners, subcontracts, developer and contractor agreements on smaller jobs, and letters of award that were never turned into a full contract.

Look properly before you decide. Often the clause isn't in the work order at all. It sits in the general conditions of contract, in the tender document, or in a standard form the work order says is "incorporated". It can turn up in an exchange of letters too. And a clause that only says the engineer in charge will decide disputes, with no mention of arbitration, usually isn't an arbitration agreement.

Suppose there is a clause and you sue anyway. The other side can ask the court under Section 8 to send the matter to arbitration, as long as it applies no later than its first statement on the substance of the dispute. If the defendant files a full written statement and never raises the clause, the suit generally carries on. We wouldn't bet on that. Pick the forum at the start.

The law a court applies to construction claims

Section 2(1)(c)(vi), Commercial Courts Act, 2015

The Act names construction and infrastructure contracts, tenders included, as commercial disputes in so many words. Once the specified value reaches Rs 3 lakh, a Commercial Court hears the suit. It follows the tighter procedure of the amended Code of Civil Procedure, and the judges do hold you to it.

Sections 55 and 67, Indian Contract Act, 1872

Section 55 is the delay section. If time is of the essence, the owner can end the contract for delay. If it isn't, or the owner waived it by giving extensions, all the owner can claim is compensation. And an owner who accepts late work can't claim compensation for the delay unless it gave notice of that when it accepted. Section 67 protects the contractor to the extent the owner didn't provide what the job needed, like site access, drawings, approvals, or materials the owner had promised to supply.

Sections 70, 73 and 74, Indian Contract Act

Section 73 gives damages for loss caused by breach. On a site, that usually means idle labour and machinery, or extra overheads while the owner's delays stretch the project out. Section 74 caps liquidated damages at reasonable compensation, no more than the agreed figure. Section 70 is the one contractors forget. It lets you recover fair value for extra work the owner accepted and benefited from, even if nobody ever issued a written variation order.

Sections 14, 20, 20A and 41(ha), Specific Relief Act, 1963

Courts rarely make a contractor finish building work. It would need constant supervision (Section 14). What the owner can do instead, after at least 30 days' written notice, is get another agency to complete the job and recover the cost from the defaulter. That's substituted performance under Section 20. For infrastructure projects listed in the Schedule to the Act, Section 20A and Section 41(ha) bar injunctions that would hold up or delay the project.

Section 80, Code of Civil Procedure, 1908

You can't sue the Government, or a public officer over something done in official capacity, without first giving two months' notice. Need urgent relief? The court can let you file without waiting. It'll still hear the Government before granting anything.

Running bills, the final bill, and why they get stuck

Most payment fights on a construction job come down to measurement and certification. You submit an RA bill based on measurements. The owner's engineer or architect checks and certifies it, and payment falls due within whatever period the contract gives. Trouble starts when measurements are cut, when items are struck off as outside the scope, or when certification just sits on someone's desk for months. We see that last one constantly.

If your bill has been certified, you're in good shape. A certified figure is a liquidated sum, and where there's a written contract, a suit on it may qualify as a summary suit under Order XXXVII. Uncertified bills are harder. You'll have to prove the work and what it's worth with measurement books, joint measurement records, drawings and photographs. Where the owner's engineer refused to certify without good reason, the court can fix the amount itself.

The final bill is where it all piles up. Last measurements, extra items, deductions for defects and whatever liquidated damages the owner wants to hold back all land on it together. Some owners keep the final bill hostage until you sign a "no claim" certificate. Don't let it lie unpaid for years while letters go back and forth. Limitation keeps running.

Delay, extensions of time and liquidated damages

Every delay dispute is really about cause. The owner deducts liquidated damages because the building was finished late. The contractor says the delay came from the owner's side: late handover of the site, late drawings, design changes, stop work notices, bills paid late, or approvals the owner was meant to get and didn't. Under Section 67 of the Contract Act, the contractor isn't liable for delay the owner's own failure caused.

If the site kept a hindrance register, that's often the document that decides it. Close behind come the letters asking for drawings, the dates the drawings actually arrived, and the owner's own minutes of site meetings. A contractor who didn't record hindrances at the time will struggle to prove them years later. Owners have a trap of their own. Grant extensions of time without reserving the right to liquidated damages, and the third paragraph of Section 55 may have taken that right away.

Liquidated damages aren't automatic. The court awards reasonable compensation up to the figure in the contract, and where a public interest project or an obvious loss is involved, it may treat the agreed figure itself as a fair estimate. If the contract made time of the essence but the owner kept granting extensions, courts often hold that time stopped being of the essence. Both sides should draw up a plain delay chart. Planned date, actual date, cause, and the document that proves the cause. When Advocate B.K. Singh goes through a delay claim, that chart usually shows the delay was shared. Then the real fight is over days. How many were yours, and how many were theirs?

Escalation, price variation and extra work

With a price variation clause and a formula, the claim is just arithmetic. Apply the formula to the indices for the right period. Without such a clause, the contractor generally carries the risk of prices rising during the original contract period. That changes once the project runs past that period because of the owner's breach. The extra cost of labour and materials in the extended period can then be claimed as damages under Section 73. You'll have to show the delay was the owner's, though, and prove what the increase actually was.

Extra items and deviations are a separate head. If the owner or its engineer ordered work outside the drawings and the bill of quantities, it's paid at the contract rate where one applies, and at a reasonable rate where none does. Plenty of contracts insist on written variation orders while the real instructions get given at site meetings or over the phone. Section 70 may still get you fair value for work the owner accepted and is using.

Owners and developers, watch the other side too. Contractors do sometimes dress up ordinary scope work as extra items, or claim escalation for delays they caused themselves. The original bill of quantities and the tender drawings usually answer those claims. So does the contractor's own programme. They rarely expect you to produce it.

Retention money, security deposit and bank guarantees

Retention money is a percentage cut from every bill, normally released after completion or once the defect liability period is over. Security deposit works much the same way. The dispute comes when the owner sits on both long after that period ends, usually pointing to unrelated defects or its own counter-claims. Once the period has expired and no defects were notified under the contract, the retention becomes a debt due. You can sue for it, with interest.

Performance bank guarantees are a different animal. An unconditional guarantee is the bank's own independent promise. Courts will stop it being invoked only in narrow cases: an egregious fraud the bank knows about, or encashment that would cause irretrievable injustice of an exceptional kind. An argument over whether you actually defaulted usually isn't enough. Move fast anyway. Once the money's gone, your challenge to a wrongful invocation is a claim for money, not an order stopping it.

Owners need care here as well. Invoke a guarantee for a purpose the contract doesn't allow, or after it has expired, and you're inviting a claim for wrongful invocation. Read the guarantee's own wording. Not just the contract.

No claim certificates and full and final settlements

Owners, and public bodies more than most, often won't release the final bill or the retention until the contractor signs a no claim or no dues certificate. Contractors sign. They need the money. Later they claim the balance, and the owner says the claim was given up.

The court looks at how the certificate came to be signed. A real settlement, where the contractor took a lower figure to close the dispute, binds the contractor. A certificate signed under economic pressure, as a condition for releasing dues the owner had already admitted, can be challenged. You'll have to prove the pressure, though. The best proof is a protest letter sent soon after signing. A protest that first shows up two years later, when the suit is filed, doesn't count for much.

Have to sign one to get paid? Then write to the owner straight away, the same week if you can, saying you signed under protest and listing the claims you're keeping alive. That single letter can decide whether the rest of your claim survives.

Who usually claims what

  • Contractor against owner or developer. Running and final bills that haven't been paid, extra items, escalation, idle labour and machinery, retention and security deposit, a refund of liquidated damages wrongly cut, and wrongful termination.
  • Owner or developer against contractor. Liquidated damages for delay, what it cost to get another agency to finish, the cost of putting defects right, mobilisation advances never adjusted, and owner-supplied steel or cement the contractor can't account for.
  • Subcontractor against main contractor. Unpaid bills, and nearly always a "pay when paid" clause thrown back at you that ties your payment to the client's. What such a clause does depends on its exact words. One that only fixes timing doesn't usually let the main contractor off paying forever.
  • Material suppliers. The price of cement, steel, ready mix concrete or fittings delivered to site. These often look more like a sale of goods claim than a construction one.
  • Architects and consultants. Fees for design and supervision stages already finished when the project was stopped or someone else was brought in.

How a construction claim moves through the court

Construction suits carry far more paper than most commercial cases. The preparation takes longer. Plan for that.

  1. Settle the forum first

    Go through the work order, general conditions, tender document and letters of award looking for an arbitration clause. Check whether the other side is a Government body that needs a Section 80 notice. And if you're registered as a micro or small enterprise, see whether the MSME Facilitation Council is open to you.

  2. Build the claim from the records

    Make a bill-wise statement showing what was billed, certified and paid, and the balance. Then put retention, security deposit, extra items, escalation and delay as separate heads. Every figure should point to a page in the measurement book, a certificate or a letter. No round numbers.

  3. Send the notice

    The notice sets out each head and its amount, with interest. Owners who plan to bring in another agency to finish should give the written notice of at least 30 days that Section 20 of the Specific Relief Act requires for substituted performance.

  4. Section 12A mediation

    Unless you need urgent interim relief, apply for pre-institution mediation through the Legal Services Authority. It works best when both sides accept some money is due and they're really arguing about how much.

  5. File the suit

    File a commercial suit with a statement of truth and every document you rely on. Certified bills may support a summary suit. A mix of bills, damages and escalation goes as a regular money recovery suit with the damages claim joined to it.

  6. Interim protection and evidence from the site

    Ask for orders only where you actually need them. That could be attachment before judgment if the owner is getting rid of assets, an injunction on a bank guarantee in a rare case, or a local commissioner under Order XXVI Rule 9 to record the state of the site before anyone changes it.

  7. Pleadings, disclosure and case management

    From service, the defendant has 120 days at the most to file its written statement and any counter-claim. Then comes the case management hearing. Issues are framed and a timetable for evidence is fixed.

  8. Evidence, judgment and execution

    Witnesses are usually the site engineers, the quantity surveyor and someone from accounts. After judgment, an appeal lies within 60 days under Section 13. The decree is enforced through execution under Order XXI.

The Specific Relief Act, as amended in 2018, also provides for designated special courts to hear suits about infrastructure project contracts. It directs that suits under that Act be decided within twelve months of service of summons, extendable by six months. Check whether your project is in the Schedule, and which court has been designated.

Time and costs at each stage (a rough guide)

StageCosts, other than lawyer feesUsual time
Getting the claim readyA quantity surveyor or engineer to reconcile measurements, if you need one2 to 6 weeks
Notice, or a Section 80 notice for GovernmentPostage and courierTwo months' wait for Government defendants, unless the court gives leave
Section 12A mediationA one-time fee to the Legal Services Authority, split equally and fixed by slabs of claim value under the 2018 Rules (check the current table)Up to 3 months, plus 2 more if extended
Filing the suitAd valorem court fee on the amount claimed, as per the state schedule. Confirm the figure before you file3 to 6 weeks to draft, because of the records
Local commissioner, if the court appoints oneFee fixed by the court, normally paid by whoever asked for the commissionerA few weeks to a few months
Written statement and counter-claimCosts if it's filed late with permission30 days, 120 days at the outside from service
Evidence and argumentsWitness expenses and adjournment costsOften 2 to 3 years in a construction suit
AppealCourt fee on the appeal under state lawWithin 60 days of the judgment
ExecutionProcess fees for attachment and saleMeant to be decided within 6 months, often takes longer

Which court will hear it

The Commercial Court takes the case when the specified value is Rs 3 lakh or more. For a money claim, Section 12 of the Commercial Courts Act counts what you claim plus interest up to the filing date. If the suit also asks for a declaration or an injunction, the value of that relief, and of any property involved, goes into the sum.

In Delhi, suits up to Rs 2 crore go to the District Judge (Commercial Court) in the district court complex for the area, which means Saket, Patiala House, Tis Hazari, Karkardooma, Rohini or Dwarka. Anything bigger goes to the Commercial Division of the Delhi High Court. A change to the district court limit has been under consideration, so check the current figure. In Ghaziabad and Gautam Buddh Nagar, the suit goes to the court designated as the district's Commercial Court, with appeals to the Allahabad High Court. Gurugram and Faridabad work the same way, with appeals to the Punjab and Haryana High Court. There's more on our page about which commercial court will hear your case.

On territory, a money claim can be filed where the defendant carries on business, or where any part of the cause of action arose. That covers where the contract was signed, where the site is, or where payment was due. Usually it's the site. A suit about rights in the land itself has to go where the land is.

Papers to pull together

The contract

  • The tender, letter of award or work order
  • General and special conditions, every page of them
  • Bill of quantities with the rates
  • Drawings, specifications and each approved revision

Doing the work

  • Measurement books and any joint measurement records
  • The site diary and the hindrance register, if anyone kept one
  • Minutes of site meetings and written instructions
  • Dated photos and videos showing progress

The money

  • Every RA bill and the final bill
  • Certificates from the engineer or architect
  • Payment advices, TDS certificates and GST records
  • Your retention and security deposit ledger, plus copies of any bank guarantee

Letters and emails

  • Your requests for drawings, approvals and payment
  • Extension of time applications and whatever replies came
  • Default notices and any termination letter
  • Any no claim certificate, and the protest letter if you sent one

How long you have to sue

Most construction money claims have to be filed within three years under the Limitation Act, 1963. Working out when those three years started is the hard part. For the price of work done at the defendant's request, with no time fixed for payment, Article 18 runs from when the work was done. If the contract fixes when the final bill is payable, time generally runs from that date. Damages for breach run from the breach, under Article 55.

Running bills are a trap. Each unpaid RA bill may give its own cause of action. A contractor who waits for the final bill before suing on the early ones can find some of them time-barred, unless the contract treats them as interim payments to be adjusted in the final bill. A written acknowledgment of the balance by the owner (Section 18), or a part payment recorded in writing (Section 19), starts the period afresh. Only if it comes before the period runs out, though.

Retention normally falls due when the defect liability period ends. So its clock starts later than the bills. Time spent in Section 12A mediation is left out of the count. Our guide on the time limit to recover dues walks through calculations like these.

Small contractors, developers, Government work and the NCR courts

If you're a small or mid-sized contractor registered as a micro or small enterprise, look at the MSMED Act, 2006. It covers services as well as goods. The owner has to pay within the agreed period, which can't be more than 45 days from acceptance of the work, and late payment attracts compound interest at three times the RBI bank rate. The Facilitation Council route under Section 18 is open even when the contract has no arbitration clause, because the council conciliates first and then arbitrates itself. For a plain bill claim, it's often quicker and cheaper than a suit.

Developers and private owners are usually defending on bills and claiming on delay and defects. Keep your own records of site handover, drawing issue and payments. Contractors build their case from exactly those documents. Where homebuyers are hurt too, their claims go to other forums. The developer and contractor dispute stays commercial.

Government and PSU work brings the Section 80 notice, slow internal approvals, and standard conditions that very often contain an arbitration clause. Across NCR, Delhi projects go to the Delhi courts. Projects with the Noida or Greater Noida authorities go to the Gautam Buddh Nagar court at Surajpur, Ghaziabad projects to the Ghaziabad court, and Gurugram and Faridabad projects to their own district courts. Each has its own court fee schedule and its own habits on listing. The time a commercial suit takes changes from one court to the next.

Where construction claims usually go wrong

Contractors mostly lose money because the records aren't there. Measurements agreed by word of mouth. Hindrances nobody wrote down. Extra work done on a phone call, and protest letters never sent. When Advocate B.K. Singh drafts a construction plaint, most of the time goes into rebuilding the paper trail from site engineers' diaries and old emails, because the court won't accept a round figure for idle labour or escalation without it.

Owners lose money by mixing up remedies. They terminate without the notice the contract asks for. They deduct liquidated damages and also claim the full cost of completion, or invoke the bank guarantee for something it doesn't cover. What makes an owner's claim hold up is a clean termination, a 30-day notice before a substitute agency comes in, and a proper record of what completion cost.

Both sides expect too much from interim relief. Courts are slow to stop a bank guarantee and slow to restrain work on infrastructure projects, and they won't order a contractor back to site. Frankly, plan for a money claim. Use interim orders only where the facts really back them.

An invented example: the 10 percent that never came back

This one is made up, to show how the pieces fit. A Ghaziabad civil contractor builds a warehouse for a private logistics company in Gautam Buddh Nagar, under a work order with no arbitration clause. Contract value, Rs 3.2 crore. The owner pays the running bills but holds back 10 percent retention, about Rs 32 lakh. It also refuses the final bill of Rs 41 lakh. Its reasons are a four-month delay and liquidated damages of Rs 30 lakh.

The contractor's site diary shows the owner handed over part of the site three months late and approved the revised roofing drawings six weeks after they were asked for. The owner had given two extensions without reserving liquidated damages. The contractor sends a notice and applies for mediation. There, the owner accepts the retention fell due once the defect liability period ended, but disputes some extra items. They settle on the retention and most of the final bill, with a smaller cut for one disputed item. If mediation had failed, the suit would have gone to the court designated as Commercial Court for Gautam Buddh Nagar. The delay record would have been the heart of it.

What to do this week

Find the full contract set, including any general conditions brought in by reference, and read it. Is there an arbitration clause or not? Then prepare a bill-wise statement of what's been billed, certified, paid and left outstanding, and a separate list of retention, security deposit and claims for delay or extra work. Check the dates. When each bill fell due, when the defect liability period ended, and when the owner last acknowledged the balance in writing.

Signed a no claim certificate under pressure? Send the protest letter now. If you're an owner bringing in another contractor, give the 30-day notice first. And if you're a defendant who's been served with summons, the 120-day outer limit for your written statement is already running. Our page on defending a commercial suit explains what to do.

If you'd like your contract, bills and site records looked at before you choose between mediation and a suit, send them to Advocate B.K. Singh's team through the contact page. We'll tell you plainly what we see in them.

Frequently asked questions

Can I file a civil suit for a construction dispute if there is no arbitration clause?

Yes. With no arbitration agreement, the dispute goes to a civil court. At Rs 3 lakh or more, that's a Commercial Court. Check the general conditions and tender papers first, though. The clause is often incorporated by reference.

How do I recover retention money from the owner?

Once the defect liability period is over and no defects were notified under the contract, retention usually becomes a debt due. Send a written demand, go through Section 12A mediation, then sue for the amount with interest. Limitation generally runs from the date the retention became payable.

Can the owner deduct liquidated damages for delay it caused?

No. Section 67 of the Contract Act excuses the contractor to the extent the owner didn't provide site, drawings, approvals or payments. And under Section 74, courts award only reasonable compensation up to the agreed figure.

Can I claim escalation if the contract has no escalation clause?

Usually not for the original contract period. But if the project dragged on because of the owner's breach, the extra cost during the extended period can be claimed as damages under Section 73. You'll need to prove what caused the delay and what the cost increase actually was.

I signed a no dues certificate to get my final bill. Have I lost my other claims?

Not necessarily. If you signed under economic pressure to get admitted dues released, the claim can survive. You'll have to prove that pressure, and a protest letter sent soon after signing helps a lot. A genuine negotiated settlement does bind you.

Can a court stop the owner from encashing my bank guarantee?

Only in narrow cases, like an egregious fraud or exceptional irretrievable injustice. A dispute over whether you defaulted usually won't do. If the guarantee is wrongly invoked, the normal remedy is to claim the money.

Do I need to send notice before suing a Government department for unpaid bills?

Yes. Section 80 of the Code of Civil Procedure needs two months' notice before you sue the Government or a public officer. In an urgent case the court can let you file without waiting. It'll still hear the Government before granting relief.

How long does a construction suit take in a Commercial Court?

Contested construction suits often take two to four years, because there's a lot of measurement and delay evidence to get through. Many settle earlier, at mediation or after the written statement. Certified bills can sometimes move faster as a summary suit.