In short. Yes, you can sue a government department for unpaid bills. First, though, you have to serve a notice under Section 80 of the Code of Civil Procedure, 1908 on the right officer and wait two months. Public sector companies don't need a Section 80 notice. You sue them like any company. Municipal bodies and development authorities have notice rules of their own. Registered micro and small suppliers can also go to the MSME Facilitation Council. This guide is for suppliers and contractors whose government bills are stuck. Start by finding out exactly where yours is stuck.
Is this your situation?
- You finished the work at the government site last year. The final bill is still lying somewhere in the division office.
- Every time you ring the PSU's finance section, someone says the payment is 'under process'. They've been saying it since Diwali.
- The department passed part of your bill months ago. Not a rupee of it has been released.
- The defect liability period ended long back, and your security deposit and retention money are still with them.
- Before releasing the final payment, the office put a no-claim certificate in front of you to sign. You weren't given much of a choice.
- You're a registered micro or small unit and you want the interest the law promises on late payment.
- You can't decide between a legal notice, the MSME Council, a writ and a suit, and you're worried about picking the wrong one.
Can you actually recover dues from a government department or PSU?
Yes. A government that owes money under a contract can be taken to court, the Centre and the states alike. Article 300 of the Constitution is the source. The Union sues and is sued as the Union of India, and each state under its own name. Section 79 of the Code of Civil Procedure, 1908 follows from that. Your suit names the Union of India or the state concerned. Not the department. Not the officer. Supply and works contracts with government stay commercial, too. Under the Explanation to Section 2(1)(c) of the Commercial Courts Act, 2015, a dispute keeps its commercial character even when the state or one of its agencies is a party.
What's different is the procedure. Before you sue a government, you have to serve a notice under Section 80 of the Code and wait two months. Order XXVII of the Code gives the government some procedural room, and a decree against it can't be executed until three months have gone by. PSUs, municipal bodies and development authorities each play by slightly different rules. So your first job is to pin down exactly who owes you. Apart from these extra steps, the case is built like any other money recovery suit.
In our experience, the real obstacle usually isn't legal at all. Government bills get stuck in files. A measurement nobody recorded. A completion certificate never issued. A budget head that's run dry, or an audit objection sitting unanswered on someone's desk. Recovering from a department often begins with finding the file. Notices and courts come after.
Department, PSU or statutory body: who exactly owes you?
| Who the buyer is | Notice before you sue | Name you sue in | Watch out for |
|---|---|---|---|
| A Central Government ministry or department, the railways included | Section 80 CPC, two months. In railway matters it goes to the General Manager of that railway | Union of India | For non-railway matters, the notice goes to a Secretary to the Government of India |
| A state government department, including departments of the Government of NCT of Delhi | Section 80 CPC, two months | The state, or the Government of NCT of Delhi | Notice goes to a Secretary to the state government or to the Collector of the district |
| A government company (central or state PSU incorporated under the Companies Act) | No Section 80 notice. An ordinary legal notice does the job | The company, in its own name | Treated like any other company for jurisdiction, service and execution |
| A statutory corporation or authority, like a municipal corporation or development authority | Whatever notice its own statute requires, often two months | The body, in its own name | Some statutes also cut the time to sue, often to six months. Read the Act |
| An autonomous society, university or institution funded by government | Usually no statutory notice. Check its constitution and any law that applies | The body, through its registrar or head | Often has its own dispute clause in the contract |
Writing a Section 80 notice that won't fall apart
Under Section 80(1), you can't file a suit against the government, or against a public officer over something done in his official capacity, until two months have passed since written notice was delivered to the right person or left at his office. Who's the right person? For the Central Government, a Secretary to the Government, except in railway matters, where it's the General Manager of the railway. For a state government, a Secretary to that government or the Collector of the district. The notice has to set out the cause of action, the relief you want, and your name, description and residence. Later, your plaint must state that the notice was delivered.
Two sub-sections added later take some of the edge off. Section 80(2) lets the court allow a suit without notice when urgent relief is needed, though it won't grant relief without hearing the government first. Section 80(3) stops a suit being dismissed merely for an error or defect in the notice. That protection holds if the notice identified you by name, description and residence, reached the right office, and substantially showed the cause of action and relief. One more thing in your favour. Section 15(2) of the Limitation Act, 1963 keeps the notice period out of the limitation count.
When Advocate B.K. Singh drafts a Section 80 notice for a contractor, he attaches a bill-by-bill schedule. Each bill's number goes in, with the date it was submitted, the date of measurement or acceptance, the amount passed, the deductions and the amount released. He also cites every departmental letter that admits the work or the dues. His thinking is simple. The notice will land in the dealing section. A bare demand gets a bare denial. A schedule tends to get a reconciliation, and once in a while, a payment. Our page on the legal notice for recovery covers notice drafting more broadly.
Municipal corporations and development authorities: a different notice?
Often, yes. Plenty of statutes that set up local bodies and authorities come with their own notice clauses. Two Delhi examples are Section 478 of the Delhi Municipal Corporation Act, 1957 and Section 53B of the Delhi Development Act, 1957. Both require two months' written notice before a suit over anything done, or purporting to be done, under the Act. Both also say the suit must be filed within six months of the cause of action, except suits about immovable property. You'll find similar clauses in other states' municipal and development laws.
Whether these clauses reach a plain claim for unpaid contract bills, as opposed to a claim about something done under statutory power, is something courts have decided differently on different facts. So play safe. Send the statutory notice and a regular legal notice both, and treat the shorter period as your real deadline until someone advises you it doesn't apply. Losing a claim for want of one letter is a painful way to learn the rule.
Before suing: what actually gets a file moving inside the system?
Begin with the office that owes you. Write to the Drawing and Disbursing Officer and to the head of office. Quote the contract, the bill numbers and the dates, and ask in writing what's pending and with whom. Keep it factual. No threats yet. A specific letter puts things on record, and it often flushes out the real reason, like a completion certificate that was never issued or a budget allocation that hasn't arrived.
If your letters go unanswered, use the Right to Information Act, 2005. Ask for the status of each bill, the file notings on it, the name of the officer it's pending with and the reasons it hasn't been paid. Under Section 7(1), the public information officer has to reply within 30 days. Quite often the reply shows the bill is complete and just waiting for one signature. That's gold for a notice, a writ or a suit. For Central Government bodies there's also the CPGRAMS online grievance portal.
Look at the dispute clause in your own contract. Works contracts tend to climb in rungs. The engineer-in-charge comes first, then a superintending engineer or a dispute resolution committee, and arbitration at the top. The Department of Expenditure, Ministry of Finance, put out guidelines in June 2024 urging negotiated settlement and mediation for public procurement disputes, with a high-level committee proposed for the large ones. GeM orders work on their own clock. Once the buyer issues the receipt and acceptance certificate, payment timelines start running, and sellers get an incident and grievance process. The terms differ over time, so check the ones that governed your order on the Government e-Marketplace (GeM).
PSU payment pending? Try the MSME Facilitation Council
Micro and small enterprises registered on the Udyam portal get real muscle from the Micro, Small and Medium Enterprises Development Act, 2006, and it works against government buyers as well as private ones. Under Section 15, the buyer must pay on the agreed date. That date can't be more than 45 days after it accepted your goods or services. With no agreement at all, it's the 15th day. Pay late and Section 16 kicks in. The buyer owes compound interest, with monthly rests, at three times the bank rate notified by the Reserve Bank of India. A civil court rarely gives you that much.
Section 18 lets you refer the dispute to the Micro and Small Enterprises Facilitation Council. The Council tries conciliation first and then arbitrates. You file online through the MSME Samadhaan portal. In Gujarat State Civil Supplies Corporation v Mahakali Foods (2022), the Supreme Court held that this route overrides an arbitration clause in the contract. That matters, because nearly every government contract has one. Courts have also said the supplier should be registered when the contract is made. Registration taken later may not help for earlier supplies. Limitation applies here as well (Silpi Industries v Kerala State Road Transport Corporation, 2021). If yours is a pure works contract, check the current position before going this way. Whether such contracts fall within the MSMED Act's delayed payment provisions has been fought over in the courts.
Against a PSU, Section 19 is the big one. A buyer that wants to challenge the Council's award in court has to deposit 75 percent of the awarded amount first. Public sector buyers that appeal almost by habit tend to think twice when three-quarters of the money has to go in upfront. Our guide comparing DIAC arbitration with the MSME Facilitation Council helps you choose between the two.
And if the contract has an arbitration clause?
Most government and PSU contracts have one, older works contracts especially. File a suit anyway and the department or PSU can apply under Section 8 of the Arbitration and Conciliation Act, 1996 to send the dispute to arbitration. The court will usually agree. So read the general and special conditions of contract before you pick a forum.
Two things have shifted lately. In November 2024, a Constitution Bench of the Supreme Court struck at clauses that let a public sector party name a sole arbitrator by itself, or that make the contractor choose from a list the PSU drew up. Such clauses, it said, break the rule of equal treatment of parties. The ruling governs appointments made after the judgment. Then there's the 2024 Finance Ministry advice that public procurement contracts shouldn't carry arbitration clauses as a matter of routine. Expect more new contracts to send disputes to mediation and the courts. Arbitration petitions under Sections 9, 11 and 34 are handled on our network site, arbitrationlawyer.in.
Writ petition or civil suit: which fits government dues?
Writs under Article 226 of the Constitution are filed directly in the High Court. They can move faster than a suit. They're a poor fit for disputed facts, though. The leading case is ABL International v Export Credit Guarantee Corporation of India (2004). There the Supreme Court allowed that a contractual money claim against the state or an instrumentality can be heard in writ, where the facts aren't seriously in dispute and the state has behaved arbitrarily. Even then, the High Court may tell you to go and file a civil suit. That discretion stays with it.
The textbook writ case is an admitted bill. The work's done, measurements recorded, the bill passed and sanctioned, and the money hasn't been released for a year or more with no reason given. The textbook suit case is a disputed bill, where the department says the work was defective, claims deductions or penalties, or argues over quantities. Don't sit on a writ, either. Long delay can sink it. If your claim has admitted and disputed parts, a writ for the admitted portion and a suit or arbitration for the rest is sometimes possible. Get advice before you split a claim, though.
Provisions that govern suits against the government
Order XXVII, Code of Civil Procedure, 1908
Rule 5 lets the court give the government reasonable time to answer the plaint, so it can communicate through proper channels. Rule 5B asks the court, in suits against the government or a public officer, to make an effort right at the start to help the parties settle. In a commercial suit, the 120-day outer limit for the written statement still applies. Courts haven't carved out a general exemption for government defendants.
Section 82, Code of Civil Procedure, 1908
No execution can issue on a decree against the Union, a state or a public officer sued over an official act until the decree has stayed unsatisfied for three months from its date. That gap gives the government time to arrange payment through its own channels.
Section 15(2), Limitation Act, 1963
Where you must give notice before suing, as under Section 80, the notice period is left out when limitation is calculated. For most money claims, the basic period is still three years.
Sections 15 to 19, MSMED Act, 2006
The buyer pays within the agreed period, and never later than 45 days. If it's late, it owes compound interest at three times the bank rate. The supplier can go to the Facilitation Council. And a buyer who wants to challenge the award must first deposit 75 percent of it.
Recovering from a government department, step by step
Put the whole bill file together
Collect the contract, work orders, measurement records, running and final bills, inspection or acceptance certificates, the completion certificate and every letter. Then draw up a bill-wise statement of what's due. Don't leave out retention money and the security deposit.
Find out where the bill is stuck
Write to the paying office, and file an RTI application asking for the bill's status and file notings. If something's missing from your side, like a pending document, sort it out before you escalate.
Serve the Section 80 notice, plus any statutory notice
Get the notice to the correct officer and keep proof of delivery. Serve any notice the authority's own statute demands as well. With a PSU company, a regular legal notice to its registered office and the contracting unit is enough.
Pick the forum
Your options are a civil suit, the MSME Facilitation Council (if you're a registered micro or small supplier), arbitration under the contract, or a writ for admitted dues. Which one turns on the contract, your registration status and whether the dues are disputed.
Apply for Section 12A mediation where you'll sue
For a commercial suit, apply for pre-institution mediation unless you need urgent relief. Government bodies do take part, and the 2024 Finance Ministry guidelines encourage them to settle.
File once the notice period is over
File after the two months under Section 80 have passed, and say in the plaint that notice was served. If the contract or an acknowledgment fixes the amount, see whether a summary suit is possible. Our guide on summary suits against a government body explains when that works.
Get to decree, then execute
Push the suit through pleadings, case management and evidence. After the decree, let the three months under Section 82 run, then apply for execution, usually by attaching funds held for the department. Our page on execution of decree has the detail.
How long each stage takes and what it costs
| Stage | Usual time | Costs other than lawyers' fees |
|---|---|---|
| Internal escalation and RTI | 30 days for an RTI reply. Letters can take longer | A nominal RTI fee. Check the current fee for that public authority |
| Section 80 notice period | Two months from delivery (not counted for limitation) | Courier and delivery charges |
| Section 12A mediation | Up to 3 months, plus 2 more if extended | A modest fee set by the legal services authority. Check the current schedule |
| MSME Facilitation Council | The Act contemplates 90 days from reference. In practice it's often longer | No court fee. A small filing fee or none, depending on the state. Check |
| Civil suit to judgment | Often 2 to 4 years against government defendants in Delhi NCR, because settlement approvals and evidence take time | Ad valorem court fee on the claim under the state schedule. Check the current one |
| Writ petition in the High Court | Anywhere from a few months to a few years, depending on the bench and whether facts are disputed | A fixed writ court fee, far lower than for a suit. Check the High Court's current rules |
| Execution of a decree | Begins three months after decree under Section 82, then usually a few months more | Process fees |
Where do you file against a department or PSU?
Section 20 of the Code governs territorial jurisdiction. Against the Union or a state, the safest anchor is where the cause of action arose. That could be where the contract was awarded or signed, where the supplies went or the work was done, or where the bills were payable. Take a contract awarded by a Delhi office for work at a Ghaziabad site, with bills paid from Delhi. Both places may have jurisdiction. The contract may also have a clause choosing one. Our guide on filing a recovery suit when the debtor is in another city explains how courts weigh such facts.
A PSU set up as a company gets no special handling. The Explanation to Section 20 applies to it as it would to any corporation. So if your claim arose where the PSU keeps a regional office or unit, that's where you file, and its corporate office in another city doesn't come into it. Then value. Claims of Rs 3 lakh or more are commercial suits. Delhi sends those up to Rs 2 crore to the District Judge (Commercial Court), and anything bigger to the Commercial Division of the Delhi High Court. That limit may change, so check it. Writs are different. Under Article 226(2), you go to the High Court in whose territory the cause of action arose, wholly or in part.
Papers to collect for a claim against a government buyer
The contract itself
- The tender notice, your bid, the letter of award or acceptance, and the signed agreement
- General and special conditions of contract, particularly the dispute and arbitration clauses
- Work orders, supply orders, the GeM contract, and any amendments or extensions of time
Proof you did the work and billed it
- Measurement book entries, or joint measurement records
- Inspection notes, receipt and acceptance certificates, and the completion certificate
- Running and final bills carrying the office's receiving stamp
- Statements of what was passed, what was deducted and what was actually released
Letters, and where things stand
- Letters and emails exchanged with the department or PSU, above all any that admit the work or the dues
- Your RTI applications, the replies and any file notings you got
- The Section 80 or statutory notice, with proof it was delivered
- Your Udyam registration certificate, if you're a micro or small enterprise
A made-up example: the Ghaziabad electrical contractor and the hospital department
What follows is invented, not a real file. A Sahibabad electrical contractor, registered as a small enterprise, wins a contract from a department of the Government of NCT of Delhi for electrical work at a government hospital in East Delhi. It finishes, and the department takes the work over in August 2024. By mid-2026 the final bill of Rs 64 lakh is still unpaid. So is the Rs 9 lakh security deposit. The division office says the same thing on every call. 'Under process.'
The contractor starts with an RTI application. The reply is revealing. The division passed the final bill for Rs 58 lakh after deductions, and it's been waiting eight months for a fund allocation. The security deposit is held up because somebody recorded the defect liability period wrongly. The contractor writes to the department with the correct dates. Then it serves a Section 80 notice on the Secretary of the department, attaching a bill-wise schedule and the RTI reply.
The contractor has three ways forward. The Rs 58 lakh that the department itself has passed and admitted on file is a natural fit for a writ in the Delhi High Court. The Rs 6 lakh of deductions is disputed, and that needs a forum where evidence can be led. Then there's the MSME route. The contractor's Udyam registration came before the contract, so it can take the entire amount, with Section 16 interest under the MSMED Act, to the Facilitation Council. On advice, that's what it does. Faced with a 75 percent deposit if it ever wants to challenge an award, the department asks to talk settlement. The talks may go nowhere. Still, the pressure has shifted. It now sits with the contractor rather than in the file.
How contractors and suppliers lose good claims
- Notice to the wrong officer, or no notice at all. A suit against the government filed without a valid Section 80 notice, and without leave under Section 80(2), can be rejected. Writing to the local executive engineer isn't notice to a Secretary.
- Letting limitation run while the file crawls. A pending file doesn't stop the clock. A departmental letter restarts it as an acknowledgment under Section 18 of the Limitation Act only if it admits liability. One saying the matter is 'being examined' may not count. Our guide on the time limit for recovering unpaid dues explains how it works.
- Signing a no-claim certificate and saying nothing. Offices sometimes want a no-claim or no-dues certificate before they'll release the final payment. Courts have accepted that a certificate signed under economic pressure doesn't always kill the claim, but you have to be able to prove the pressure. Advocate B.K. Singh tells contractors in this spot to send a protest letter the same day. It should record that the certificate was signed only to get the admitted dues released, and that every other claim is reserved.
- Forgetting retention money and the security deposit. Together they're often bigger than the last bill, and they get left out of notices all the time. Our guide on recovering retention money deals with them.
- Suing the officer personally. A suit for contract dues lies against the Union, the state or the body. Not against the officer who sat on your payment, unless he acted outside his official capacity.
What to do this week about a stuck government bill
Put together the bill-wise statement and the file. Send the paying office a specific written query. If nothing comes back in a reasonable time, file an RTI application. Compare your Udyam registration date with the contract date. Read the dispute clause. Then work out how much of the three-year limitation is left on your oldest bill. If time's short, serve the Section 80 notice now. The two months won't count against limitation.
Think about interest from day one. On old government dues it can be a big slice of the claim. Courts can award interest under Section 34 of the Code, and registered micro and small suppliers get the higher statutory rate under the MSMED Act. Our guide on how much interest you can claim on unpaid dues explains both. When talks and notices get you nowhere, the money recovery suit is still the general route, and that page sets out its stages.
Want your contract, bills and letters with the department looked at before you choose between a notice, the MSME Council, a writ and a suit? Share them with Advocate B.K. Singh's team through the contact page.
Frequently asked questions
Is a Section 80 notice needed before suing a PSU like a government oil or power company?
No. A government company incorporated under the Companies Act isn't 'the Government' for Section 80, so an ordinary legal notice will do. Do check whether the contract itself demands a notice, or some dispute resolution step, before proceedings.
Can I claim interest on a delayed government payment?
You can. A civil court can award interest under Section 34 of the Code, at the contract rate or a reasonable commercial rate. If you're a registered micro or small enterprise, Section 16 of the MSMED Act gives you compound interest at three times the RBI bank rate.
Can a government department be sued in a summary suit?
Yes, if the claim fits Order XXXVII, say a debt or liquidated demand under a written contract. You still need the Section 80 notice. Government defendants often get leave to defend when they raise a plausible dispute, so how much you gain depends on how clearly liability is admitted.
What if the department says it has no funds?
That's not a defence to a contract claim. It explains the delay. It doesn't cancel the debt. Once you hold a decree or an award, the government has to provide for it, and execution can go ahead after the three-month period under Section 82.
Can I stop work if the department isn't paying running bills?
Only if the contract or the law allows it, and only after notice. Stopping without a contractual basis can expose you to termination and penalties. Read the suspension and termination clauses, and put the payment defaults on record in writing, before you take that step.
Does the GeM portal have its own remedy for late payment?
GeM sets payment timelines for buyers once the receipt and acceptance certificate is issued, and it runs an incident management process for seller complaints. If that doesn't get you paid, the usual legal remedies stay open, the MSME Council included for registered suppliers.
Can I recover my earnest money or performance guarantee in the same claim?
Yes. Earnest money, performance security, retention money and security deposits that have been wrongly held back can go into the same notice and the same proceeding as the unpaid bills. If a bank guarantee is about to be wrongly invoked, you may need urgent relief from the court.
How long does the government take to pay after a decree?
Execution can't start until three months after the decree, under Section 82 of the Code. Many departments pay within that window or soon after, especially when the alternative is attachment of their funds. Some appeal instead. An appeal against a commercial court decree has to be filed within 60 days.